Half year Report and Accounts - 31 December 2025
Released
Released
Announcement PDF
WIN Metals Ltd
A.C.N. 648 687 094
Half-Year Report
for the 6 months ended 31 December 2025
2
WIN Metals Ltd
The directors of WIN Metals Ltd (“Company”) (“WIN”) submit herewith the half-year report of WIN and its subsidiaries (“Group”)
(“Consolidated Entity”) for the six months ended 31 December 2025. Pursuant to the provisions of the Corporations Act 2001,
the directors report as follows:
Directors
The names of the directors of the company during or since the end of the half-year are:
Mr Johannes Stig (Steve) Norregaard – Appointed 1 July 2021
Mr Andrew Parker – Appointed 1 July 2021
Ms Felicity Repacholi – Appointed 1 July 2021
Mr Scott Perry – Appointed 1 July 2021
All directors have served on the Board for the period 1 July 2025 to 31 December 2025.
Principal activities
During the financial period, the principal continuing activities of the Group consisted of the exploration and evaluation of
resource projects.
REVIEW OF OPERATIONS
The Company continued its revitalised focus on gold during the period with the opportune purchase of the Radio Gold Project
completed in September 2025. The purchase was made on favourable terms with a strategy aimed towards a production restart
scenario set to capitalise on the substantial investment made by previous owners which includes the mine itself on care and
maintenance, mining equipment and light vehicles, staff accommodation and a partially built processing facility. WIN
immediately got to work with a drill program aimed at evaluating near mine open pit opportunities with some encouraging first
passresults leadingtoa Mineral Resource Estimate announced inJanuary2026.These initial outcomes provide strongvalidation
for the acquisition and demonstrate the opportunity that WIN seeks to realise.
Building on WIN’s first drill program at its Butchers Creek Gold Project in late 2024 WIN has advanced the Project through early
technical studies and an initial scoping study with encouraging results from this announced in November 2025. The Company
continues to progress this Project with permitting activities ongoing and a planned drill program at the Golden Crown deposit
designed to enable this Resource to be incorporated into an updated feasibility study, which is expected to further reinforce the
substantial upside to the initial scoping study outcomes.
The Company completed two capital raisings during the period to support its activities. These placements were well supported
by new incoming shareholders and by existing shareholders.
The Company retains its exposure to both nickel and lithium at the Mt Edwards Project with a limited expenditure strategy in
place. Of note, a recent uptick in Li and Ni commodity prices and sentiment has been evident in the latter months of the period
following Indonesia’s announced intended tightening of supply. The Company maintains its belief in the inherent value of these
assets.
3
WIN Metals Ltd
Figure 1: WIN Metals Project Map
4
WIN Metals Ltd
Radio Gold Project (WIN 100%)
Project Acquisition:
In September 2025, WIN completed the acquisition of the Radio Gold Mine, located north of Southern Cross in
Western Australia, from Top Global Mining Pty Ltd. The transaction included a total cash payment of $500,000 plus
GST and share consideration of $400,000 plus GST via the issue of 20 million shares at $0.02 per share. A deferred
consideration arrangement also applies, comprising a stepped royalty of 5% of net smelter returns up to the first
18,000 ounces produced, followed by a trailing 1.5% royalty thereafter.
The acquisition included:
• Modern underground decline access (330m of decline and 200m of ore development)
• Existing surface ore stockpiles
• Partially constructed 500ktpa processing facility
• Operational offices, workshop, underground mining equipment and accommodation facilities
• Mining Lease M77/633, Prospecting Licence P77/4492, and Miscellaneous Licence L77/81
Figure 2: Radio Mine Site Infrastructure
5
WIN Metals Ltd
WIN has rapidly advanced on-ground activities, with a 10m x 10m RC grade control and exploration drilling program
to delineate near-surface resources and extend the resource footprint both along strike and down dip of known
mineralisation. The results from this drilling have underpinned the updated Mineral Resource Estimate (MRE) for
the project to feed into the economic mining studies. In parallel, the Company aims to capitalise on prior
infrastructure investment by evaluating options for a fit-for-purpose crushing, grinding, and gravity circuit, including
potential leaching of gravity tails to maximise gold recovery.
WIN also plans to systematically evaluate historic prospects across its broader tenure. While many of these
prospects are small, high-grade occurrences that may lack standalone development potential, the Company sees
significant opportunity to consolidate and unlock value by advancing these assets through targeted exploration and
portfolio development.
Exploration and evaluation:
WIN’s first RC drilling program delivered exceptional drilling results at the Radio Gold Project, confirming shallow
and depth extensions of high-grade gold mineralisation at the Repeater Prospect, located approximately 100m
north of the main Radio mineralised body and nowinterpreted as its northern continuation, with standout intercepts
including 1m @ 33.95g/t Au, 2m @ 30.58g/t Au (including 1m @ 50.8g/t Au) and 1m @ 10.11g/t Au from ~100m,
highlighting a system that remains open and largely untested at depth.
Notable intercepts reported during the period include:
• 2m @ 30.58g/t Au from 25m, including 1m @ 50.8g/t Au (25RDRC108)
• 1m @ 33.95g/t Au from 27m (25RDRC055)
• 1m @ 30.65g/t Au from 51m (25RDRC040)
• 2m @ 13.95g/t Au from 26m (25RDRC037)
• 1m @ 15.53g/t Au from 36m (25RDRC103)
• 1m @ 14.00g/t Au from ~70m (25RDRC063)
• 1m @ 11.40g/t Au from 46m (25RDRC102)
• 1m @ 10.11g/t Au from ~100m (25RDRC082)
These results confirm multiple stacked, high‑grade lodes with down‑dip continuity and support the interpretation
of a plunging high‑grade shoot underpinning the maiden MRE at Repeater. The shallow nature of much of the
mineralisation, immediately adjacent to existing Radio mine infrastructure, positions Repeater as a potential near
term source of high‑grade ore for both open pit and potential underground mining scenarios.
6
WIN Metals Ltd
Figure 3: Repeater drill section A-'A against preliminary optimised pit shell outline looking northeast (+/- 5m
section window)
High-grade mineralisation at Radio extended both down-dip and along strike, including 2m @ 5.21g/t Au from 102m
(25RDRC093), located approximately 20m beyond the current 10 Level development, confirming high-grade
mineralisation continues south beyond existing mine development and supporting the definition of a maiden
Mineral Resource at Repeater.
Mineral Resource Estimate Update:
The updated MRE declared in January 2026 now stands at 345,000 tonnes at 3.70g/t gold for 41,000 ounces,
representing a 46% increase in contained ounces compared to the 2018 estimate (see Table 1 below). The increase
is driven by WIN’s successful drill program delivering maiden MRE for the Repeater and Radio South and Green
Harp domains, which collectively contribute 114,000 tonnes at 3.50g/t gold for 12,800 ounces.
Importantly, approximately half of the updated MRE, being 21,000 ounces are now classified as Indicated,
reflecting improved confidence in geological continuity and data quality. Any potential near term development of
the Radio Gold Project will remain subject to completion of further technical, economic and regulatory studies,
receipt of all required approvals, and a positive production decision. The Company is currently working towards a
potential development decision before end of Q2 2026. No Ore Reserves have yet been estimated for the Radio
Gold Project and no production target or forecast financial information is being reported at this time.
7
WIN Metals Ltd
Table 1: Radio Gold Project Mineral Resource Summary
Deposit Resource Classification Tonnes Au g/t Contained Gold (Oz)
East Indicated 37,000 3.63 4,300
Main Indicated 66,000 4.69 10,000
Repeater Indicated 48,000 3.90 6,000
Radio South Indicated 10,000 2.21 700
East Inferred 44,000 5.35 7,500
Main Inferred 81,000 2.45 6,300
Repeater Inferred 32,000 3.86 3,900
Radio South Inferred 17,000 2.91 1,600
Green Harp Inferred 7,000 2.34 600
Mill Inferred 3,000 0.92 100
Total Indicated + Inferred 345,000 3.70 41,000
Note: Figures are rounded and reported at 0.5g/t cut-off to 50m below surface (open pit) and 1.0g/t below 50m of surface.
Table 2: Radio Gold Project Mineral Resource Summary by Resource Classification
Deposit Resource Classification Tonnes Au g/t Contained Gold (Oz)
Radio Gold Project
Indicated 161,000 4.06 21,000
Inferred 184,000 3.39 20,000
Total Indicated + Inferred 345,000 3.70 41,000
Note: Figures are rounded and reported at 0.5g/t cut-off to 50m below surface (open pit) and 1.0g/t below 50m of surface.
Butchers Creek Gold Project (WIN 100%, 97% M80/106 & M80/315)
Exploration and Evaluation Activities:
In November 2025, WIN completed a transformational Scoping Study at the Butchers Creek Gold Project,
confirming a 9-year Life of Mine with forecast production of approximately 200koz of gold, underpinned by strong
operating margins, high-grade feed, and a simple, conventional processing flowsheet delivering robust project
economics, based on a conservative gold price assumption of A$5,385 per ounce.
Key outcomes of the Scoping Study include (based on a gold price assumption of A$5,385 per ounce):
• Life of Mine: 9 years
• Ore processed: 3.29Mt @ 2.0g/t Au
• Recovered gold: ~200koz
• Average production: ~33kozpa during steady state operations
• Peak production: ~37koz in Year 5
• Pre-production capital: A$142 million
• Free cash flow: A$288 million (pre-tax)
• NPV (8%): A$143 million (pre-tax)
• IRR: 25% (pre-tax)
• AISC: A$3,032/oz
• Payback period: Approximately 3.5 years from commencement of production
8
WIN Metals Ltd
The Study is based on the Butchers Creek Mineral Deposit Resource only, which demonstrates the potential to
develop a conventional gold operation comprising open pit and underground mining supported by a 600ktpa CIL
processing plant and associated infrastructure a simple processing flowsheet and an open pit strip ratio of
approximately 11.8. The robust financial outcomes reflect strong operating margins derived from high-grade feed,
with the Project generating meaningful free cash flow over the Life of Mine at a gold price assumption of A$5,385
per ounce.
The Scoping Study also confirms that the Project benefits from low technical complexity, with no requirement for
novel processing methods, and highlights opportunities to further enhance value through optimisation of mine
scheduling, potential incorporation of the nearby Golden Crown deposit, and additional resource growth from
continued exploration. These opportunities will be assessed as the Project progresses to the next level of technical
evaluation.
The Company has commenced preliminary work streams to advance permitting pathways, stakeholder
engagement and further technical studies aimed at improving confidence levels and refining development options.
The Scoping Study is a preliminary technical and economic assessment completed to a scoping level of accuracy
of approximately ±40% and does not support the estimation of Ore Reserves. The production target is based on a
combination of Indicated (approximately 96%) and Inferred (approximately 4%) Mineral Resources. While the
inclusion of Inferred Mineral Resources is not material to the financial viability of the Project, there is no certainty
that further exploration will result in the conversion of Inferred Resources to Indicated or Measured categories.
Table 3: Project Financial Sensitivity Analysis
Gold Price A$/oz $3,846 $4,615 $5,385 $6,154 $6,923
Payback first gold production Month N/A 56 41 35 32
Max negative cashflow A$M -164 -142 -142 -142 -142
Free cash flow A$M -9 131 288 436 585
NPV 8% pre-finance, pre-tax A$M -54 45 143 241 339
IRR pre-tax % N/A 14 25 34 42
9
WIN Metals Ltd
Figure 4: Butchers Creek underground mine design
Regional Field Reconnaissance Butchers Creek:
A 500m gold trend has been defined at Ruby Queen North with rock chip assays up to 5.16g/t Au, while the Emjay
gold prospect returned assays up to 23.5g/t Au; both prospects have been advanced to drill-ready status.
Figure 5: Emjay sample locations Au ppb and Au ppm in call outs
10
WIN Metals Ltd
Mt Edwards Nickel Project (WIN 100%) - Exploration and Evaluation activities
WIN controls a dominant ~240 km2
land package over the prolific nickel-producing Widgiemooltha Dome in Western Australia.
The Mt Edwards Nickel Project is positioned adjacent to key infrastructure, located just 80km south of the major regional centre
of Kalgoorlie, 30km south-west of Kambalda and along strike to the north from Wyloo’s Cassini Nickel mine.
The Mt Edwards Nickel Project is comprised of 11 separate deposits with a total MRE of 12.7Mt grading 1.43% nickel for 180,900
tonnes.
In March 2024, the Company released a Scoping Study on the Mt Edwards Nickel Project. WIN Metals commissioned the Scoping
Study for the purpose of carrying out a preliminary assessment of the technical and financial viability of a standalone nickel
mining and processing operation.
No exploration activities were undertaken at Mt Edwards during the period. Ongoing test work is examining downstream options
to produce nickel sulphate or NCM battery precursor (pCAM), with these studies expected to guide the project’s future direction.
Table 4: WIN Metals Total Nickel Mineral Resources
Deposit
Indicated Inferred TOTAL Resources
Tonne
(Mt)
Nickel
(%)
Tonne
(Mt)
Nickel
(%)
Tonne
(Mt)
Nickel
(%)
Nickel
Tonnes
Gillett* 2.27 1.35 0.87 1.16 3.14 1.30 40,770
Widgie 3* 0.51 1.34 0.22 1.95 0.73 1.53 11,200
Widgie Townsite* 1.65 1.60 0.85 1.38 2.50 1.53 38,260
Armstrong* 0.95 1.45 0.01 1.04 0.96 1.44 13,820
132N 0.03 2.90 0.43 1.90 0.46 2.00 9,050
Cooke 0.15 1.30 0.15 1.30 2,000
Inco Boundary 0.46 1.20 0.46 1.20 5,590
McEwen 1.13 1.35 1.13 1.35 15,340
McEwen
Hangingwall
1.92 1.36 1.92 1.36 26,110
Mt Edwards 26N 0.87 1.43 0.87 1.43 12,400
Zabel 0.27 1.94 0.05 2.04 0.33 1.96 6,360
TOTAL 5.68 1.48 6.97 1.39 12.66 1.43 180,900
*All Resources reported at 1.0% Ni cut-off except for WTS, Widgie 3, Gillett and Armstrong which are reported at 0.7% Ni cut- off. Tonnes
and grade have been rounded to reflect the relative uncertainty of the estimates.
Faraday-Trainline Lithium Project (WIN 100%) - Exploration and Evaluation
activities
The Faraday-Trainline Lithium Project is located in the “lithium corridor” between Mt Marion to the north and Pioneer Dome to
the south in Widgiemooltha, Western Australia. The project hosts the Faraday-Trainline Lithium Deposit as well as four
prospects Farson, Atomic 3, Voyager and Gemini. The Faraday-Trainline lithium Mineral Resource Estimate (MRE) amounts to
1.96Mt @ 0.69% Li2O including a high-grade, near surface zone of 373kt @ 1.00% Li2O with a Measured and Indicated Mineral
Resources total of 1.57Mt @ 0.71% Li2O.
11
WIN Metals Ltd
Table 5 - WIN Metals Mt Edwards Lithium Mineral Resource Estimates
Deposit
Measured Indicated Inferred TOTAL Resources
Tonne (kt) Li2O (%) Tonne (kt) Li2O (%) Tonne (kt) Li2O (%) Tonne (kt) Li2O (%) Li2O Tonnes
Faraday 550 0.75 250 0.66 220 0.61 1,020 0.7 7,100
Trainline - - 780 0.69 160 0.63 940 0.68 6,300
TOTAL 550 0.75 1,020 0.68 390 0.62 1,960 0.69 13,500
Reported above a cut-off grade of 0.30% Li2O to a depth of 310mRL (65m below surface) and 0.50% Li2O below 310mRL to 250mRL. Tonnes and
grade have been rounded to reflect the relative uncertainty of the estimates.
No exploration activities were undertaken at Faraday-Trainline during the period. Metallurgical test work was advancing aiming
at optimising float recoveries in addition to targeting potential byproduct value.
Corporate
December 2025 Placement Capital Raising Completed for $5.5m
On 12 December 2025, WIN successfully completed a A$5.5 million capital raising through the issue of 157,142,857 new fully
paid ordinary shares at A$0.035 per share, together with one free attaching option for every two shares issued in February 2026
following receipt of shareholder approval received at a General Meeting held on 28 January 2026. The options are listed and are
exercisable at $0.07 per share with a two-year expiry. The placement was oversubscribed and strongly supported by existing and
new sophisticated investors. GBA Capital acted as Lead Manager to the placement.
These funds will be applied to the second phase of drilling and resource definition activities at the Radio Gold Project, drilling
and evaluation work at the Golden Crown deposit to support future studies at the Butchers Creek Gold Project, and general
working capital to support the Company’s growth strategy.
August 2025 Placement Capital Raising Completed for $2.35m
In August 2025 WIN Metals successfully completed an oversubscribed Placement on 26 August 2025, raising gross proceeds of
A$2.35 million through the issue of 117,514,599 shares at A$0.02 per share. Subsequently following receipt of shareholder
approval at the Annual General Meeting held on 26 November 2025, the Company issued one attaching unlisted option for every
two shares issued under the Placement. These options are exercisable at A$0.04 each and will expire two years from the date of
issue.
Funds from the Placement were utilised for the acquisition and first phase of drilling at the newly acquired Radio Gold project,
evaluation and study works on the Butchers Creek project and general working capital.
Divestment of Non-Core Assets for $0.5m
As announced on 9 September 2025, WIN finalised the sale of non-core assets to Auric Mining Ltd, including the divestment of
nickel interests in the Munda tenement (M15/87). A final payment of $500,000 was received from Auric in November 2025. The
Munda nickel deposit was not part of WIN’s short or medium-term development plans for Mt Edwards, and this transaction
unlocks latent value for WIN while preserving the bulk of its nickel resource at Mt Edwards, enabling greater focus on advancing
gold assets at Radio, Butchers Creek and pursuing new growth opportunities.
Future Work
A follow up drill program is planned at Radio for quarter 1 2026 to evaluate the full extent of the mineralisation at Repeater and
to infill the resource of Radio main to assist in advancing the technical and economic evaluation of development of the Project
and targeting a potential development decision by end of Q2 2026.
In addition, drilling is planned at the Butchers Creek Gold Project, Golden Crown deposit. A resultant upgraded resource at
Golden Crown to complement a preliminary feasibility study on the Butchers Creek Project leading to an expected substantial
improvement to the project outcomes, along with associated development permitting activities and approvals.
12
WIN Metals Ltd
Finances
Available cash on hand as of 31 December 2025 totalled A$5.934 million.
Issued Capital
The total number of shares on issue at 31 December 2025 was 857,091,636.
Dividends
There were no dividends paid, recommended or declared during the current financial period.
Competent Person Statement
The information in this announcement that relates to exploration results and sampling techniques is based on and fairly
represents information and supporting documentation compiled by Mr William Stewart, who is a full-time employee of WIN
Metals Ltd. Mr Stewart is a member of the Australian Institute of Metallurgy and Mining (member no 224335) and Australian
Institute of Geoscientists (member no 4982). Mr Stewart has sufficient experience that is relevant to the style of mineralisation
and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the
2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Stewart
consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.
Compliance Statement
The information in this report is extracted from the ASX Announcements listed in the table below, which are also available on
the Company’s website at www.winmetals.com.au and the ASX website www.asx.com under the code WIN.
DateReleased ASXAnnouncement
29/1/2026 RadioGoldProjectMineralResourceUpdate
27/1/2026 WINMetalsQuarterlyActivitiesReport&Appendix5B
21/1/2026 RadioGoldProjectExplorationResults
12/12/2025 WINWellFundedTowardsGoldProductionFollowingPlacement
8/12/2025 RepeaterContinuestoDeliverShallowHigh-GradeHits
2/12/2025 High-GradeExtensionalHitsConfirmGrowthatRadioGold
12/11/2025 ButchersCreekGoldProjectDeliversRobustScopingStudy
5/11/2025 OutstandingFirstDrillResultsatRadioGoldProject
31/10/2025 WINMetalsQuarterlyActivitiesReport&Appendix5B
21/10/2025 RadioGoldProjectHistoricExplorationResults
24/9/2025 WINCompletesAcquisitionofRadioGoldMine
9/9/2025 WINFinalisesSaleofNon-CoreAssets
21/8/2025 WINtoAccelerateDrillProgramatRadioFollowingPlacement
14/8/2025 ReconnaissanceGeneratesDrillTargetatRubyQueenNorth
4/8/2025 WINtoAcquireHighGradeRadioGoldMine
15/7/2025 HighgradeGoldConfirmsEmjayProspectivity
1/7/2025 Saleofnon-coreassetsyield$1.4MforWINtoadvancegoldAssets
13
WIN Metals Ltd
16/4/2025 WINadvancesButchersCreektowardsdevelopmentfollowingresourceupdate
08/11/2023 375%GrowthinFaraday-TrainlineLithiumMineralResource
The Company confirms that it is not aware of any new information or data that materially affects the information included in the
original market announcements and that all material assumptions and technical parameters underpinning the estimates in the
market announcements continue to apply and have not materially changed. The Company confirms that the form and context
in which the Competent Persons’ findings are presented have not been materially modified from the original market
announcements.
Forward Looking Statement
Caution regarding Forward Looking Information. This document contains forward looking statements concerning WIN Metals
Ltd. Forward looking statements are not statements of historical fact and actual events and results may differ materially from
those described in the forward-looking statements as a result of a variety of risks, uncertainties, and other factors. Forward
looking statements in this document are based on WIN's beliefs, opinions and estimates as of the dates the forward-looking
statements are made, and no obligation is assumed to update forward looking statements if these beliefs, opinions, or estimates
should change or to reflect other future developments.
AUDITOR’S INDEPENDENCE DECLARATION
The auditor’s independence declaration is included on page 14 of the half-year report.
Signed in accordance with a resolution of the directors made pursuant to s.306(3) of the Corporations Act 2001.
On behalf of the directors,
Steve Norregaard
Managing Director
Perth, 13 March 2026
Liability limited by a scheme approved under Professional Standards Legislation.
Member of Deloitte Asia Pacific Limited and the Deloitte organisation.
13 March 2026
The Board of Directors
WIN Metals Ltd
Level 4, 220 St Georges Terrace
Perth WA 6000
Dear Board Members
Auditor’s Independence Declaration to WIN Metals Ltd
In accordance with section 307C of the Corporations Act 2001, I am pleased to provide the following
declaration of independence to the directors of WIN Metals Ltd.
As lead audit partner for the review of the financial report of WIN Metals Ltd for the year half year ended
31 December 2025, I declare that to the best of my knowledge and belief, there have been no
contraventions of:
• The auditor independence requirements of the Corporations Act 2001 in relation to the review; and
• Any applicable code of professional conduct in relation to the review.
Yours faithfully
DELOITTE TOUCHE TOHMATSU
N H Gordon
Partner
Chartered Accountants
Deloitte Touche Tohmatsu
ABN 74 490 121 060
Tower 2
Brookfield Place
123 St Georges Terrace
Perth WA 6000
GPO Box A46
Perth WA 6837 Australia
Tel: +61 8 9365 7000
Fax: +61 8 9365 7001
www.deloitte.com.au
14
Liability limited by a scheme approved under Professional Standards Legislation.
Member of Deloitte Asia Pacific Limited and the Deloitte organisation.
Independent Auditor’s Review Report to the members of
WIN Metals Ltd
Conclusion
We have reviewed the half-year financial report of WIN Metals Ltd (the “Company”) and its subsidiaries the
“Group”), which comprises the condensed consolidated statement of financial position as at 31 December
2025, and the condensed consolidated statement of profit or loss and comprehensive income, the
condensed consolidated statement of cash flows and the condensed consolidated statement of changes in
equity for the half-year ended on that date, notes to the financial statements, including material accounting
policy information and other explanatory information, and the directors’ declaration.
Based on our review, which is not an audit, we have not become aware of any matter that makes us believe
that the accompanying half-year financial report of the Group does not comply with the Corporations Act
2001, including:
• Giving a true and fair view of the Group’s financial position as at 31 December 2025 and of its performance
for the half-year ended on that date; and
• Complying with Accounting Standard AASB 134 Interim Financial Reporting and the Corporations
Regulations 2001.
Basis for Conclusion
We conducted our review in accordance with ASRE 2410 Review of a Financial Report Performed by the
Independent Auditor of the Entity. Our responsibilities are further described in the Auditor’s Responsibilities
for the Review of the Half-year Financial Report section of our report. We are independent of the Group in
accordance with the auditor independence requirements of the Corporations Act 2001 and the ethical
requirements of the APES 110 Code of Ethics for Professional Accountants (including Independence
Standards) issued by the Accounting Professional and Ethical Standards Board (“the Code”) that are relevant
to our audit of the annual financial report of public interest entities in Australia. We have also fulfilled our
other ethical responsibilities in accordance with the Code.
We confirm that the independence declaration required by the Corporations Act 2001 which has been given
to the directors of the Company, would be in the same terms if given to the directors as at the time of this
auditor’s review report.
Material Uncertainty Related to Going Concern
We draw attention to Note 2 in the half-year financial report which indicates that the Group has incurred
losses of $2,037,729 (31 Dec 2024: $32,543,180 which includes a $30,823,857 impairment loss) and
experienced net cash outflows from operating and investing activities of $3,723,731 (31 Dec 2024:
$2,485,898) for the half-year ended 31 December 2025. These conditions, along with other matters set forth
in Note 2, indicate that a material uncertainty exists that may cast significant doubt over the Group’s ability to
continue as a going concern. Our conclusion is not modified in respect of this matter.
Deloitte Touche Tohmatsu
ABN 74 490 121 060
Tower 2
Brookfield Place
123 St Georges Terrace
Perth WA 6000
GPO Box A46
Perth WA 6837 Australia
Tel: +61 8 9365 7000
Fax: +61 8 9365 7001
www.deloitte.com.au
15
Directors’ Responsibilities for the Half-year Financial Report
The directors of the Company are responsible for the preparation of the half-year financial report that gives a
true and fair view in accordance with Australian Accounting Standards and the Corporations Act 2001 and for
such internal control as the directors determine is necessary to enable the preparation of the half-year financial
report that gives a true and fair view and is free from material misstatement, whether due to fraud or error.
Auditor’s Responsibilities for the Review of the Half-year Financial Report
Our responsibility is to express a conclusion on the half-year financial report based on our review. ASRE 2410
requires us to conclude whether we have become aware of any matter that makes us believe that the half-
year financial report is not in accordance with the Corporations Act 2001 including giving a true and fair view
of the Group’s financial position as at 31 December 2025 and its performance for the half-year ended on that
date, and complying with Accounting Standard AASB 134 Interim Financial Reporting and the Corporations
Regulations 2001.
A review of a half-year financial report consists of making enquiries, primarily of persons responsible for
financial and accounting matters, and applying analytical and other review procedures. A review is
substantially less in scope than an audit conducted in accordance with Australian Auditing Standards and
consequently does not enable us to obtain assurance that we would become aware of all significant matters
that might be identified in an audit. Accordingly, we do not express an audit opinion.
DELOITTE TOUCHE TOHMATSU
N H Gordon
Partner
Chartered Accountants
Perth, 13 March 2026
16
17
WIN Metals Ltd
Directors’ declaration
The directors declare that:
(a) the attached financial statements and notes comply with the Corporations Act 2001, Australian Accounting Standard
AASB 134 Interim Financial Reporting, the Corporations Regulations 2001 and other mandatory professional
reporting requirements; and
(b) in the directors’ opinion, there are reasonable grounds to believe that the company will be able to pay its debts as
and when they become due and payable; and
(c) in the directors’ opinion, the attached financial statements and notes thereto are in accordance with the
Corporations Act 2001, including compliance with accounting standards and giving a true and fair view of the
financial position and performance of the con
Share your feedback