Exceptional 132N Massive Sulphide Hit Confirmed
Released
Released
Announcement PDF
ASX Announcement
13 September 2023
Exceptional 132N Massive Sulphide Hit
Confirmed
Highlights
•
Exceptionally high-grade nickel mineralisation at 132N, previously reported by XRF in 23MERCD112
now confirmed by assay
23MERCD112
9.14m @ 10.44% Ni, 0.75% Cu, 0.13% Co, 1.93g/t 3PGE from 330.00m
Incl
2.61m @ 18.88% Ni, 0.48% Cu, 0.23% Co, 0.65g/t 3PGE from 335.44m
Figure 1 23MERCD112 Individual assay results from disseminated to massive sulphide mineralisation.
Managing Director, Steve Norregaard said: “Widgie attracted great interest with the core sample displayed at
our Diggers booth this year for good reason. We are delighted to share the assay results for 23MERCD112
validating portable XRF readings announced on the 11 August 2023. This hole drilled through the lower zone of
the current 132N resource shape confirms the presence of exceptionally high-grade mineralisation.”
ABN 77 648 687 094
Level 4, 220 St Georges Tce
Perth, WA 6000
PO BOX 7713
Cloisters Square WA 6850
T: +61 8 6381 7250
F: +61 8 6381 7299
info@widgienickel.com.au
www.widgienickel.com.au
1
Exceptional 132N Massive Sulphide Hit Confirmed
13 September 2023
Widgie Nickel Limited (ASX: WIN, “Widgie” or “the Company”) is pleased to provide an update on the 132N
deposit (132N) resource infill drilling program with assays received from hole 23MERCD112. The results
confirm previously reported Portable X-Ray Fluorescence (pXRF) readings (ASX announcement of 11 August
2023 - “Exceptional 132N Massive sulphide Hit”).
132N is located on Mining Lease M15/101, 6km north-west of the Widgiemooltha township. Access is via the
Coolgardie-Esperance Highway, 63km south of Coolgardie. 132N forms part of the Company’s Mt Edwards
Project, covering a significant land holding within the Widgiemooltha Nickel Province between historic
Spargoville nickel mines to the north and the operating Cassini nickel mine to the south.
Figure 2 Widgie Nickel’s, Mt Edwards Tenure and Mineral Resources
132N Geology and Geological Interpretation
132N lies to the north of the Widgiemooltha Dome, a double plunging anticlinal structure cored by a deformed
granitoid. The pre-deformation stratigraphy at 132N consists of a basaltic footwall and ultramafic hanging wall
with minor sediment units found within the footwall basalt unit.
ABN 77 648 687 094
Level 4, 220 St Georges Tce
Perth, WA 6000
PO BOX 7713
Cloisters Square WA 6850
T: +61 8 6381 7250
F: +61 8 6381 7299
info@widgienickel.com.au
www.widgienickel.com.au
2
Exceptional 132N Massive Sulphide Hit Confirmed
13 September 2023
The nickel sulphide mineralisation plunges to the north at 132N. Generally, the massive sulphide mineralisation
is found upon the basal contact where it grades into disseminated sulphides within the ultramafic hanging wall.
Depth of weathering varies from 5m-30m depth at 132N.
Discussion of Results
Resource Infill result from 23MERCD112 shows the potential of the 132N deposit to deliver thick, ultra highgrade nickel mineralisation. 23MERCD112 was fast tracked for assay with the remainder of the 132N resource
definition drilling program being processed currently, with assays expected in October 2023.
Figure 3 Long section of 132N Deposit, 23MERCD112 intercept 9.14m @ 10.44% Ni
The position as shown in Figure 3 demonstrates the location of the intercept coincides with an expected
mineralised zone. 23MERCD112 was designed to increase drill density and increase geological confidence.
Table 1 23MERCD112 mineralisation intercept (0.5% Ni cut-off)
Hole ID
Hole Type
Prospect
From (m)
To (m)
DHW (m)
Ni pct
Cu pct
Co pct
As ppm
3PGE (g/t)
23MERCD112
DD
132N
330
339.14
9.14
10.44
0.75
0.13
173
1.93
incl.
DD
132N
335.44
338.05
2.61
18.88
0.48
0.23
26
0.65
Significant intercepts above 0.5% Ni, in places includes internal dilution to allow for grade continuity.
RC = Reverse circulation, DD = Diamond Core Tail
3PGE = Au ppm + Pt ppm + Pd ppm
Table 2 Collar details for holes reported in this ASX announcement
Hole ID
Tenement
Prospect
Drill Type
Total Depth (m)
Easting (m)
Northing (m)
RL (m)
Dipo
Azio
23MERCD112
M15/101
132N
RC/DD
369.5
361255
6519176
384
-49.3
264.7
Co-ordinates and azimuths in MGA (GDA94) Zone 51
RC = Reverse circulation, DD = Diamond Core
ABN 77 648 687 094
Level 4, 220 St Georges Tce
Perth, WA 6000
PO BOX 7713
Cloisters Square WA 6850
T: +61 8 6381 7250
F: +61 8 6381 7299
info@widgienickel.com.au
www.widgienickel.com.au
3
Exceptional 132N Massive Sulphide Hit Confirmed
13 September 2023
Competent Person Statement
The information in this announcement that relates to exploration results and sampling techniques is based on
and fairly represents information and supporting documentation compiled by Mr William Stewart, who is a fulltime employee of Widgie Nickel Limited. Mr Stewart is a member of the Australian Institute of Metallurgy and
Mining (member no 224335) and Australian Institute of Geoscientists (member no 4982). Mr Stewart has
sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to
the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Stewart consents to the
inclusion in the report of the matters based on his information in the form and context in which it appears.
Compliance Statement
The Company confirms that it is not aware of any new information or data that materially affects the information
included in the original market announcements and that all material assumptions and technical parameters
underpinning the estimates in the market announcements continue to apply and have not materially changed. The
Company confirms that the form and context in which the Competent Persons’ findings are presented have not
been materially modified from the original market announcements.
Approved by: Board of Widgie Nickel Ltd
For further details please contact
Steve Norregaard
Managing Director
steve@widgienickel.com.au
0472 621 529
ABN 77 648 687 094
Level 4, 220 St Georges Tce
Perth, WA 6000
PO BOX 7713
Cloisters Square WA 6850
-ENDSShane Murphy
FTI Consulting
shane.murphy@fticonsulting.com
0420 945 291
T: +61 8 6381 7250
F: +61 8 6381 7299
info@widgienickel.com.au
www.widgienickel.com.au
4
Exceptional 132N Massive Sulphide Hit Confirmed
13 September 2023
Table 1 information in accordance with JORC 2012: Mt Edwards Nickel Exploration
Section 1 Sampling Techniques and Data
(Criteria in this section apply to all succeeding sections.)
Section 1 Sampling Techniques and Data
Criteria
Sampling
techniques
JORC Code Explanation
Nature and quality of sampling (e.g., cut
channels, random chips, or specific
specialised industry standard
measurement tools appropriate to the
minerals under investigation, such as down
hole gamma sondes, or handheld XRF
instruments, etc). These examples should
not be taken as limiting the broad meaning
of sampling
Include reference to measures taken to
ensure sample representivity and the
appropriate calibration of any
measurement tools or systems used.
Commentary
All new data collected from 132N discussed in this report is in relation
to the recently completed reverse circulation (RC) and diamond
drilling (DD) and sampling program conducted between 28 July 2023
and 30 July 2023.
All RC samples have been acquired at one metre intervals from a
chute beneath a cyclone on the RC drill rig. Sample size was then
reduced through a cone sample splitter. Two identical sub-samples
have been captured in pre-numbered calico bags, with typical masses
ranging between 2 and 3.5kg. Care was taken to ensure that both
original sub-samples and duplicate sub-samples have been collected
representatively, and therefore are of equal quantities. The remainder
of the sample (the reject) has been retained in the short term in
sample piles at the drill site.
Samples assessed as prospective for nickel mineralisation have been
assayed at single metre sample intervals.
Aspects of the determination of
mineralisation that are Material to the
Public Report. In cases where ‘industry
standard’ work has been done this would
be relatively simple (e.g., ‘reverse
circulation drilling was used to obtain 1 m
samples from which 3 kg was pulverised to
produce a 30 g charge for fire assay’). In
other cases more explanation may be
required, such as where there is coarse
gold that has inherent sampling problems.
Unusual commodities or
mineralisation types (e.g., submarine
nodules) may warrant disclosure of
detailed information.
Drilling
Techniques
Drill type (e.g., core, reverse circulation,
open- hole hammer, rotary air blast, auger,
Bangka, sonic, etc) and details (e.g., core
diameter, triple or standard tube, depth of
diamond tails, face-sampling bit or other
type, whether core is oriented and if so, by
what method, etc).
A mineralised sample is defined as that which when tested in a
laboratory would be expected to have an assay returned above 0.3%
nickel.
DD samples of NQ2 size quarter core have been acquired according
to logged lithological and mineralisation boundaries at lengths
between 0.3 metres to 1.3 metres.
No other measurement tools related to sampling have been used in
the holes for sampling other than directional/orientation survey tools.
Base metal, multi-element analysis was completed using a 4-acid
digest with ICP-OES finish for 9 elements. PGE’s (Au, Pt and Pd)
analysis was completed via 25g charge Fire Assay with an ICP-MS
finish.
One (1) drillhole has been completed and reported in this
announcement for 369.5m.
The RC rig is a KWL350 with a face sampling auxiliary compressor
and booster. Drill rods are 6 metres long and drill bit diameter is
143mm, and hence so is the size of drillhole diameter. Holes have
been drilled at a nominal dip angle of -60° with varying azimuth angles
to orthogonally intercept the interpreted favourable geological
contact zones.
The DD rig is an Austex 1550 drilling NQ2 with standard tube. Core is
oriented using Reflex ACT III tool.
ABN 77 648 687 094
Level 4, 220 St Georges Tce
Perth, WA 6000
PO BOX 7713
Cloisters Square WA 6850
T: +61 8 6381 7250
F: +61 8 6381 7299
info@widgienickel.com.au
www.widgienickel.com.au
5
Exceptional 132N Massive Sulphide Hit Confirmed
13 September 2023
Section 1 Sampling Techniques and Data
Drill Sample
Recovery
Method of recording and assessing core
and chip sample recoveries and results
assessed.
Measures taken to maximise sample
recovery and ensure representative nature
of the samples.
Whether a relationship exists between
sample recovery and grade and whether
sample bias may have occurred due to
preferential loss/gain of fine/coarse
material.
Logging
The sample recovery is logged by a geologist during drilling, and
recoveries have been considered acceptable.
Minor sample loss was recognised while sampling the first metre of
some drillholes due to very fine grain size of the surface and nearsurface material.
No relationship between sample recovery and grade has been
recognised.
Whether core and chip samples have been
geologically and geotechnically logged to a
level of detail to support appropriate
Mineral Resource estimation, mining
studies and metallurgical studies.
All RC drillholes have been geologically logged for lithology,
weathering, alteration, and mineralogy. All samples have been logged
in the field at the time of drilling and sampling (both quantitatively and
qualitatively where viable), with spoil material and sieved rock chips
assessed. All RC holes are photographed.
Whether logging is qualitative or
quantitative in nature. Core (or costean,
channel, etc) photography.
All DD holes have been geologically logged (both quantitatively and
qualitatively) for lithology, weathering, alteration and mineralogy and
sampled following drilling. All DD holes are photographed.
The total length and percentage of the
relevant intersections logged.
The total length of RC drilling for drilling as reported is 150 metres,
with a total of 219.5 metres of DD completed.
Geochemical analysis of each hole has been correlated back to
logged geology for validation.
Sub-sampling
techniques
and sample
preparation
If core, whether cut or sawn and whether
quarter, half or all core taken.
The sample preparation technique carried out in the field is
considered industry best standard practice and was completed by the
geologist.
If non-core, whether riffled, tube sampled,
rotary split, etc and whether sampled wet
or dry.
RC: Samples collected at 1 metre intervals from a cyclone-mounted
cone splitter to yield a 2 to 3 kg sub-samples.
For all sample types, the nature, quality and
appropriateness of the sample preparation
technique.
DD: Samples of NQ2 size core at lengths between 0.3 metres to 1.3
metres have been cut with an Almonte core saw and quarter core
submitted for analysis. With the remaining ¾ core retained for
metallurgical testing.
Individual samples have been weighed as received and then dried in
a gas oven for up to 12 hours at 105°C.
Samples >3 kg’s have been riffle split 50:50 and excess discarded. All
samples have been then pulverised in a LM5 pulveriser for 5 minutes
to achieve 85% passing 75um. 1:50 grind checks have been
performed to verify passing was achieved.
A 300g split was taken at the bowl upon completion of the grind and
sent to the next facility for assay. The remainder of the sample (now
pulverised) was bagged and retained until further notice.
For each submitted sample, the remaining sample (material) less the
aliquot used for analysis has been retained, with the majority retained
and returned to the original calico bag and a nominal 300g portion
split into a pulp packet for future reference.
ABN 77 648 687 094
Level 4, 220 St Georges Tce
Perth, WA 6000
PO BOX 7713
Cloisters Square WA 6850
T: +61 8 6381 7250
F: +61 8 6381 7299
info@widgienickel.com.au
www.widgienickel.com.au
6
Exceptional 132N Massive Sulphide Hit Confirmed
13 September 2023
Section 1 Sampling Techniques and Data
Quality of
assay data and
laboratory
tests
Quality control procedures adopted for all
sub-sampling stages to maximise
representivity of samples.
Measures taken to ensure that the
sampling is representative of the in situ
material collected, including for instance
results for field duplicate/second-half
sampling.
Whether sample sizes are appropriate to
the grain size of the material being
sampled.
The nature, quality and appropriateness of
the assaying and laboratory procedures
used and whether the technique is
considered partial or total.
For geophysical tools, spectrometers,
handheld XRF instruments, etc, the
parameters used in determining the
analysis including instrument make and
model, reading times, calibrations factors
applied and their derivation, etc.
Nature of quality control procedures
adopted (e.g., standards, blanks,
duplicates, external laboratory checks) and
whether acceptable levels of accuracy (i.e.,
lack of bias) and precision have been
established.
Widgie Nickel has established QAQC procedures for all drilling and
sampling programs including the use of commercial Certified
Reference Material (CRM) as field and laboratory standards, field and
laboratory duplicates and blanks.
Nickel sulphide CRM samples have been inserted into the batches by
the geologist, at a nominal rate of 5% of the total samples.
Field duplicate samples have been taken in visibly mineralised zones,
at a rate of 2% of total samples.
Samples of blank material have been submitted immediately after
visibly mineralised zones at a nominal rate of 5% of the total samples.
Sample size is considered appropriate to the grain size of the material
being sampled.
Assaying was Intertek Genalysis with standards and duplicates
reported in the sample batches.
Individual samples have been assayed for a suite of 33 elements
including nickel related analytes as per the laboratory’s procedure for
a 4-acid digestion (HCL/HCLO4/HF/HNO3) followed by an Induced
Coupled Plasma Mass Spectrometry (ICP-OES) analytical technique.
PGE’s (Au, Pt and Pd) analysis was completed via Fire Assay with a
Mass Spectrometry (MS) finish.
Internal sample quality control analysis was then conducted on each
sample and on the batch by the laboratory.
Results have been reported to Widgie Nickel in CSV, PDF and SIF
formats.
A detailed QAQC analysis was carried out with all results assessed
for repeatability and meeting expected values relevant to nickel and
related elements. Any failures or discrepancies were followed up as
required.
Verification of
sampling and
assaying
The verification of significant intersections
by either independent or alternative
company personnel.
The use of twinned holes
The verification of significant intersections
by either independent or alternative
company personnel.
Discuss any adjustment to assay data
Assay results are provided by the laboratory to Widgie Nickel in CSV,
PDF and SIF formats, and then validated and entered into the
database managed by an external contractor. Backups of the
database are stored both in and out of office.
Assay, Sample ID and logging data are matched and validated using
filters in the drill database. The data is further visually validated by
Widgie Nickel geologists and database staff.
Significant intersections are verified by senior Widgie Nickel
geologists.
There has been no validation and cross checking of laboratory
performance at this stage.
No adjustment of assay data has been undertaken.
Location of
data points
Accuracy and quality of surveys used to
locate drillholes (collar and down-hole
surveys), trenches, mine workings and
other locations used in Mineral Resource
estimation.
Specification of the grid system used
ABN 77 648 687 094
Level 4, 220 St Georges Tce
Perth, WA 6000
PO BOX 7713
Cloisters Square WA 6850
A handheld GPS has been used to determine the drillhole collar
locations, accurate to 3m.
MGA94_51S is the grid system used in this program.
Downhole survey using Reflex Sprint IQ gyro survey equipment was
conducted during the program by the drilling contractor.
T: +61 8 6381 7250
F: +61 8 6381 7299
info@widgienickel.com.au
www.widgienickel.com.au
7
Exceptional 132N Massive Sulphide Hit Confirmed
13 September 2023
Section 1 Sampling Techniques and Data
Quality and adequacy of topographic
control
Downhole Gyro survey data have been converted from true north to
MGA94 Zone51S and saved into the data base. The formulas used
are:
Grid Azimuth = True Azimuth + Grid Convergence.
Grid Azimuth = Magnetic Azimuth + Magnetic Declination + Grid
Convergence.
The Magnetic Declination and Grid Convergence have been
calculated with and accuracy to 1 decimal place using plugins in
QGIS.
Magnetic Declination = 0.8
Grid Convergence = -0.7
Topographic control is provided by collar surveys drilled in this
campaign, and by either collar survey or historical topographic
surveys for historical data. Topographic control is considered
adequate.
Data spacing
and
distribution.
Data spacing for reporting of Exploration
Results
Whether the data spacing and distribution
is sufficient to establish the degree of
geological and grade continuity appropriate
for the Mineral Resource and Ore Reserve
estimation procedure(s) and classifications
applied.
Whether sample compositing has been
applied
Orientation of
data in relation
to geological
structure
Whether the orientation of sampling
achieves unbiased sampling of possible
structures and the extent to which this is
known, considering the deposit type.
If the relationship between the drilling
orientation and the orientation of key
mineralised structures is considered to
have introduced a sampling bias, this
should be assessed and reported if
material.
All RC drillholes have been sampled at 1 metre intervals down hole.
All DD drillhole have been sampled at between 0.3 and 1.3 metres.
Drillholes have been designed and completed to infill and extend
known mineralisation, with a nominal drillhole spacing of recent and
historical drilling of 30 to 60 metres. The drillhole spacing is
considered sufficient to establish the degree of geological and grade
continuity appropriate to estimate and report an Inferred Mineral
Resource or better.
Compositing has been applied only as an interim measure to
determine nickel grade anomalism, with follow up assay of individual
samples undertaken where anomalism is detected.
In the Mt. Edwards region, nickel mineralisation is typically located on
the favourable basal contact zone of ultramafic rock units overlaying
metabasalt rock units. All drillholes have been planned at varying dip
and azimuth angles, in order to where possible orthogonally intercept
the interpreted favourable geological contact zones.
Geological information (including structural) from both historical
geological mapping as well as current geological mapping have been
used during the planning of these drillholes. Due to the steep
orientation of the mineralised zones in some place, there will be some
exaggeration of the width of intercepts.
Sample
security
The measures taken to ensure sample
security.
All RC samples were transported by truck directly to Intertek
Kalgoorlie laboratory at 12 Keogh Way, West Kalgoorlie, WA, for
submission. All DD samples were transported to the Widgie Nickel
warehouse in Carlisle, WA, with cut samples then transported to
Intertek Perth at 544 Bickley Road, Maddington. Sample security was
not considered a significant risk to the project. No specific measures
have been taken by Widgie Nickel to ensure sample security beyond
the normal chain of custody for a sample submission.
Audits or
reviews
The results of any audits or reviews of
sampling techniques and data.
A review of the exploration program was undertaken prior to the drill
program by Widgie Nickel Geology management. Regular reviews and
site visits have been made during the conduct of drill program. Staff
and contract geologists have been based on site prior to, during and
on completion of the drill and sample program to ensure proper
quality control as per the modern mining industry standards.
ABN 77 648 687 094
Level 4, 220 St Georges Tce
Perth, WA 6000
PO BOX 7713
Cloisters Square WA 6850
T: +61 8 6381 7250
F: +61 8 6381 7299
info@widgienickel.com.au
www.widgienickel.com.au
8
Exceptional 132N Massive Sulphide Hit Confirmed
13 September 2023
Section 2 Reporting of Exploration Results
(Criteria listed in section 1, and where relevant, in sections 3 and 4, also apply to this section.)
Section 2 Reporting of Exploration Results
Criteria
JORC Code Explanation
Mineral
tenement and
land tenure
status
Type, reference name/number, location and
ownership including agreements or material
issues with third parties such as joint ventures,
partnerships, overriding royalties, native title
interests, historical sites, wilderness or
national park and environmental settings.
Commentary
The 132N deposit is located on M15/101, which is held by Mt
Edwards Critical Metals Pty Ltd.
The security of the tenure held at the time of
reporting along with any known impediments
to obtaining a licence to operate in the area.
Exploration
done by other
parties
Acknowledgment and appraisal of exploration
by other parties.
Widgie Nickel has held M15/101 since July 2021; hence all prior
work has been conducted by other parties.
The ground has a long history of exploration and mining and has
been explored for nickel since the 1960s, initially by Western
Mining Corporation. Numerous companies have taken varying
interests in the project area since this time.
The most recent drilling undertaken at 132N prior to that by
Widgie, was completed by Neometals in 2019.
Historical exploration results and data quality have been
considered during the planning stage of drill locations on
M15/101 for this drilling program, and results of the program are
being used to validate historic data.
Geology
Deposit type, geological setting and style of
mineralisation.
The geology at 132N comprises steeply dipping and folded
sequences of ultramafic rock, metabasalt rock units and
intermittent meta-sedimentary units.
Contact zones between ultramafic rock and metabasalt are
considered favourable zones for nickel mineralisation.
The mineralisation is characterised as primary nickel within
massive and disseminated sulphides, interpreted as being
hosted within ultramafic lava flows and associated thermal
erosion channels.
Drillhole
information
A summary of all information material to the
understanding of the exploration results
including a tabulation of the following
information for all Material drillholes:
easting and northing of the drillhole collar
elevation or RL (Reduced Level – elevation
above sea level in metres) of the drillhole
collar
One (1) drillhole have been completed. This hole has a DD tail
have has been completed on the RC pre-collar.
All drillholes have been drilled at a nominal -60° +/- 5° dip at
varying azimuth angles.
Relevant drillhole information has been tabled in the report
including hole ID, drill type, drill collar location, elevation, drilled
depth, azimuth, dip and respective tenement number.
The drillhole has been tabulated within the accompanying report.
dip and azimuth of the hole
down hole length and interception depth
hole length.
If the exclusion of this information is justified
on the basis that the information is not
Material and this exclusion does not detract
from the understanding of the report, the
Competent Person should clearly explain why
this is the case.
ABN 77 648 687 094
Level 4, 220 St Georges Tce
Perth, WA 6000
PO BOX 7713
Cloisters Square WA 6850
T: +61 8 6381 7250
F: +61 8 6381 7299
info@widgienickel.com.au
www.widgienickel.com.au
9
Exceptional 132N Massive Sulphide Hit Confirmed
13 September 2023
Section 2 Reporting of Exploration Results
Data
aggregation
methods
In reporting Exploration Results, weighting
averaging techniques, maximum and/or
minimum grade truncations (e.g., cutting of
high grades) and cut-off grades are usually
Material and should be stated.
Where aggregate intercepts incorporate short
lengths of high grade results and longer
lengths of low grade results, the procedure
used for such aggregation should be stated
and some typical examples of such
aggregations should be shown in detail.
The significant intervals reported are an average nickel grade
weighted by the interval length. Where the significant interval
includes internal dilution, this is included in the weighted average
grade.
No top-cuts have been applied.
No metal equivalents have been reported.
The assumptions used for any reporting of
metal equivalent values should be clearly
stated.
These relationships are particularly important
in the reporting of Exploration Results
Nickel mineralisation is hosted in the ultramafic rock unit close
to the metabasalt contact zones.
If the geometry of the mineralisation with
respect to the drillhole angle is known, its
nature should be reported.
All drilling is angled to best intercept the favourable contact
zones between ultramafic rock and metabasalt rock units to best
as possible test true widths of mineralisation.
If it is not known and only the down hole
lengths are reported, there should be a clear
statement to this effect (e.g., ‘down hole
length, true width not known’).
Due to the ~85° orientation of the mineralised zones there is an
exaggeration of the width of intercepts. True width is expected
to be 50%-60% of the downhole intercept.
Diagrams
Appropriate maps and sections (with scales)
and tabulations of intercepts should be
included for any significant discovery being
reported These should include, but not be
limited to a plan view of drillhole collar
locations and appropriate sectional views.
A map of the drilling program location and tenement relative to
the total Mt Edwards project is shown in the report. Cross
sections and long sections are shown for several of the drillholes
completed.
Balanced
reporting
Where comprehensive reporting of all
Exploration Results is not practicable,
representative reporting of both low and high
grades and/or widths should be practiced to
avoid misleading reporting of Exploration
Results.
All results have been reported.
Other
substantive
exploration data
Other exploration data, if meaningful and
material, should be reported including (but not
limited
to):
geological
observations;
geophysical survey results; geochemical
survey results; bulk samples – size and method
of treatment; metallurgical test results; bulk
density, groundwater, geotechnical and rock
characteristics potential deleterious or
contaminating substances.
No further exploration data has been collected at this stage.
Further work
The nature and scale of planned further work
(e.g., tests for lateral extensions or large scale
step out drilling.
All 132N core will be submitted for laboratory analysis. Once
assay results are received detailed modelling of the
mineralisation will occur.
Diagrams clearly highlighting the areas of
possible extensions, including the main
geological interpretations and future drilling
areas, provided this information is not
commercially sensitive.
Detailed interpretation of the results is underway as all assays
have been received and passed quality control checks. Upon
completion of the drilling 50mm PVC casing has been inserted
into some of the drillholes at both locations to enable downhole
electromagnetic (DHEM) geophysical surveys to be conducted.
Relationship
between
mineralisation
widths and
intercept
lengths
Results will be tabulated to assist with mineral resource update
of 132N in the near term.
ABN 77 648 687 094
Level 4, 220 St Georges Tce
Perth, WA 6000
PO BOX 7713
Cloisters Square WA 6850
T: +61 8 6381 7250
F: +61 8 6381 7299
info@widgienickel.com.au
www.widgienickel.com.au
10
Share your feedback
Discover